Koli İnşaat completed structural and finishing works covering 8,800 m² at the seafront Vuni Palace Hotel in Kyrenia in 7 months.

7 ay
Construction time
8.800 m²
Construction area
2008
Year of delivery
Vuni Palace Hotel — Girne, KKTC
Client
Client: Oscar Group
Construction area
Construction area: 8.800 m²
Status
Status: Completed

During the seven-month Vuni Palace Hotel project, Koli İnşaat undertook structural and finishing works covering 8,800 m². The works for Oscar Group at the seafront hotel on Reyhanlı Street in Kyrenia were completed in 2008.

The five-star hotel had 176 rooms at the time of the works and consisted of a main building and ancillary buildings. The scope included guest rooms, communal areas and service areas. Works in the restaurant, bar, pool, wellness centre, beach and pier areas were also coordinated.

The slope of the site, seafront working conditions and winter weather presented challenges. At peak activity, 30–100 people worked on site. At the handover stage, guest rooms, communal areas, outdoor areas and technical infrastructure were checked to prepare the hotel for operation.

Key features

Three technical decisions that set the project apart from its peers. Each one affects operating costs directly across the building's service life.

Structural and finishing works

Koli İnşaat undertook structural and finishing works in the main building and ancillary buildings.

Structural and finishing works

8,800 m² work area

The construction works carried out by the company covered 8,800 m².

8,800 m² work area

176 rooms at the time of the works

The hotel had a total of 176 rooms during Koli İnşaat’s work on the project.

176 rooms at the time of the works

Considering a similar building? — Request a free site visit

Project development process

The steps ran in order; at every stage the next one began only after client approval.

  1. 01

    Site layout review

    The site layout was reviewed in terms of its connection to the city, the relationship between the beach and outdoor areas, and communal links between the buildings.

  2. 02

    Structural and finishing works

    Structural and finishing works were carried out in the main building and ancillary buildings, covering guest rooms, communal areas and service areas.

  3. 03

    Communal and outdoor area works

    Works in the restaurant, bar, pool and wellness centre were coordinated alongside works in the beach and pier areas.

  4. 04

    Inspection and handover

    Guest rooms, communal areas, outdoor areas and technical infrastructure were checked, and the hotel was handed over ready for operation.

Problems met on site and their solutions

No site goes exactly as planned. What matters is solving the problem before it reaches the budget and the schedule.

Problem met

  • Sloping terrain

    The slope of the terrain was one of the conditions that made site work difficult.

  • Working by the sea

    Seafront working conditions presented difficulties during construction.

  • Winter conditions

    The part of the work carried out during winter made site operations more difficult.

Solution applied

  • Working in tiers

    Work areas on the sloping terrain were divided into tiers.

  • Waterproofing and damp-proofing

    Waterproofing and damp-proofing were applied to the seafront building.

  • Scheduling around the weather

    During winter, outdoor works were rescheduled for days with suitable weather.

Our other projects

All Projects

Everything you need to know

We work in every area of the construction industry: superstructure, industrial facilities, pipelines and storage facilities, infrastructure and environment, and military facility construction. We also serve in interior fit-out and fine works with our experienced crews.

Yes. Sourcing and using quality materials is among the first of our principles. We take on material supply together with the application and work with materials fit for advanced technology.

Yes. From the architectural and structural design to the permit process, from shell construction to fine works, we run every stage under a single contract. If you prefer, we can take on the construction part only.

Absolutely. In projects where we work with the client's own architectural team, we take on the structural, mechanical and electrical coordination and review the project details together at every stage.

After the first meeting and the on-site visit we give a preliminary budget based on a unit price per m², and once the preliminary design is complete, a detailed item-by-item estimate. The site visit is free.

Let's talk about your project — the site visit and preliminary budget are free

A call or a form is enough. We will get back to you shortly and set a day for an on-site visit.